Production health settings
Set the rules that decide when a production order is On Track, At Risk or Delayed, plus override and alert options.
The Manage Health Rules page for production lets you define when a production order is shown as On Track, At Risk or Delayed, who can override that status, and how long alerts stay visible.
SettingsProduction
Permission: UPDATE_BRAND_PRODUCTION
Health is calculated from these settings each time it is shown, so after you save, the production overview, summaries and alerts update with the new thresholds.
Change the rules
Open the page
From the left sidebar, click Settings, then Production. The page opens on the Meanings tab.

Open a tab
Click Delayed, At Risk, Override, Alerts or Milestones to see its rules.

Change a value
Type a number in a field or turn a toggle on or off. Toggles that are greyed out are always on or always off and cannot be changed.

Click "Save settings"
Click Save settings at the bottom right of the page. The page shows "Production health settings saved".

Tip
Click Reset to defaults to put every field back to the values below. Nothing is saved until you click Save settings.
Meanings tab
A read-only reminder of what each health status means.
| Status | Meaning |
|---|---|
| On Track | No known production timeline issue detected. |
| At Risk | Warning signs detected. Production may slip if no action is taken. |
| Delayed | Agreed ex-factory has been missed or a later ex-factory date has been confirmed. |
Delayed tab
Delayed Rules define when production should be marked as Delayed.
| Rule | What it does | Default |
|---|---|---|
| Agreed ex-factory missed by more than (days) | Mark as Delayed when the agreed ex-factory date is missed by more than this many days. Allowed 0 to 365. | 0 |
| Actual ex-factory moved later than agreed | Always on. A confirmed later ex-factory date marks the order Delayed. | On, locked |
| Supplier confirms later ex-factory | Always on. A supplier-confirmed later ex-factory date marks the order Delayed. | On, locked |
| Shipment confirmed after agreed ex-factory | Always on. Goods leaving the factory later than agreed marks the order Delayed. | On, locked |
At Risk tab
At Risk Rules define when production is flagged before it becomes delayed.
| Rule | What it does | Default |
|---|---|---|
| Production start not confirmed after (days) | Mark as At Risk when production start is not confirmed this many days after the start date. Allowed 0 to 365. | 1 |
| Start date moved later than agreed | Mark as At Risk when the actual start date moves later than agreed. | On |
| Completion not confirmed within (days of ex-factory) | Mark as At Risk when production completion is not confirmed within this many days of ex-factory. Allowed 0 to 365. | 5 |
| Completion date moved later than agreed | Mark as At Risk when the actual completion date moves later than agreed. | On |
| Supplier confirmation unanswered after (hours) | Mark as At Risk when a supplier confirmation request is unanswered after this many hours. Allowed 0 to 8760. | 48 |
Override tab
Manual Override controls whether health can be changed by hand.
| Setting | What it does | Default |
|---|---|---|
| Allow health override | Allow authorised users to manually override the displayed health status. | On |
| Require reason | Require a reason whenever health is manually overridden. | On |
| Suppliers can override health | Suppliers can never override health. | Off, locked |
Alerts tab
Active Alert Settings control the alerts list.
| Setting | What it does | Default |
|---|---|---|
| Active alerts visibility period (days) | Show At Risk and Delayed items in Active Alerts for this many days. Allowed 1 to 365. | 14 |
| Immediate alerts for new Delayed items | Send an alert immediately when an item becomes Delayed. | On |
| Immediate alerts for new At Risk items | Send an alert immediately when an item becomes At Risk. | On |
Milestones tab
Upcoming Production Milestones control which milestones are listed as upcoming.
| Setting | What it does | Default |
|---|---|---|
| Milestone visibility period (days) | Show upcoming production milestones due within this many days. Allowed 1 to 365. | 7 |
| Include production start | Always on for this phase. | On, locked |
| Include production completion | Always on for this phase. | On, locked |
| Include ex-factory | Always on for this phase. | On, locked |
| Include delivery | Off for now. Delivery health is out of scope in this phase. | Off, locked |